BB Interior Finishes - Walls (repairs)   June 2024  
BB Interior Finishes - Walls (painting)   June 2024  
BB Interior Finishes - Floors (replace carpet w/ VCT) Completed June 2023 September 2023
VV Interior Finishes = Floors (terrazzo repair) Abatement of Vinyl Asbestos Tile Completed   August 2023
BB Abatement of Vinyl Asbestos Tile Completed June 2023 July 2023
BB Interior Finishes - Ceilings Completed June 2023 July 2023
VV Interior Finishes - Ceilings (Gymnasium)   June 2024  
BB ADA Compliance - Infividual Toilet Rooms   June 2024  
BB ADA Compliance - Multi-user Toilet Rooms   June 2024  
BB/VV ADA Compliance - Handrails Completed May 2023 July 2023
VV Media Center - Carpet Tiles   June 2024  
VV Media Center - Learning Commons Reconfiguration   June 2024  
VV Art Room Reconfiguration   June 2024  
VV Music Room Upgrades   June 2024  
BB Casework  Competed September 2023 October 2023
VV Casework Completed September 2023 October 2023
VV Faculty Room Upgrade   April 2024  

 

Updates

A list of projects which have been completed and that are underway for the month of February 2024.

  • Bayberry
  • Building Envelope
  • Building Interior
  • Electrical & Plumbing
  • Security Systems
  • Site Improvements
  • Valley View
Old Doors

Old doors to be refurnished

Non ADA Handrail

Non ADA compliant handrail to be updated

Valley View ADA compliant handrails completed

Bayberry Library Carpet

Bayberry Library carpeting to be replaced

Bayberry Library carpeting replacement in progress

Bayberry Library carpeting tile installation completed. 

Bayberry Asbestos Tile

Vinyl asbestos tile at Bayberry to be abated

Bayberry Asbestos Tile

Vinyl asbestos tile at Bayberry to be abated

New floor tiles replaced in Bayberry for asbestos tile abatement.

Old Ceiling Tile

Old ceiling tiles to be replaced. Tile tracks to be painted. 

Bayberry ceiling tile replacement in progress

New Bayberry ceiling tiles replaced in C Wing

Bayberry classroom casework demolition in progress

Bayberry classroom casework demolition in progress

Bayberry classroom casework completed

Valley View classroom casework demolition in progress

Valley View classroom casework completed

Valley View classroom casework completed