Building Interior

Project Status

Estimated Start

Estimated Completion
BB Interior Finishes - Walls (repairs)      
BB Interior Finishes - Walls (painting)      
BB Interior Finishes - Floors (replace carpet w/ VCT)   June 2023 September 2023
VV Interior Finishes = Floors (terrazzo repair) Abatement of Vinyl Asbestos Tile      
Abatement of Vinyl Asbestos Tile   June 2023 September 2023
BB Interior Finishes - Ceilings      
VV Interior Finishes - Ceilings (Gymnasium)      
BB ADA Compliance - Infividual Toilet Rooms      
BB ADA Compliance - Multi-user Toilet Rooms      
BB/VV ADA Compliance - Handrails   May 2023 July 2023
VV Media Center - Carpet Tiles   June 2023 September 2023
VV Media Center - Learning Commons Reconfiguration      
VV Art Room Reconfiguration      
VV Music Room Upgrades      
BB Casework       
VV Casework      
VV Faculty Room Upgrade      

 

Updates

Old Doors

Old doors to be refurnished

Old Ceiling Tile

Old ceiling tiles to be replaced. Tile tracks to be painted. 

Non ADA Handrail

Non ADA compliant handrail to be updated

Non ADA compliant handrail to be updated

Bayberry Library Carpet

Bayberry Library carpeting to be replaced

Bayberry Asbestos Tile

Vinyl asbestos tile at Bayberry to be abated

Bayberry Asbestos Tile

Vinyl asbestos tile at Bayberry to be abated