Building Interior
Project | Status |
Estimated Start |
Estimated Completion |
---|---|---|---|
BB Interior Finishes - Walls (repairs) | June 2024 | ||
BB Interior Finishes - Walls (painting) | June 2024 | ||
BB Interior Finishes - Floors (replace carpet w/ VCT) | Completed | June 2023 | September 2023 |
VV Interior Finishes = Floors (terrazzo repair) Abatement of Vinyl Asbestos Tile | Completed | August 2023 | |
BB Abatement of Vinyl Asbestos Tile | Completed | June 2023 | July 2023 |
BB Interior Finishes - Ceilings | Completed | June 2023 | July 2023 |
VV Interior Finishes - Ceilings (Gymnasium) | |||
BB ADA Compliance - Infividual Toilet Rooms | June 2024 | ||
BB ADA Compliance - Multi-user Toilet Rooms | June 2024 | ||
BB/VV ADA Compliance - Handrails | Completed | May 2023 | July 2023 |
VV Media Center - Carpet Tiles | June 2024 | ||
VV Media Center - Learning Commons Reconfiguration | June 2024 | ||
VV Art Room Reconfiguration | June 2024 | ||
VV Music Room Upgrades | June 2024 | ||
BB Casework | Competed | September 2023 | October 2023 |
VV Casework | In Progress | September 2023 | October 2023 |
VV Faculty Room Upgrade | June 2024 |
Updates
A list of projects that have been completed and which are underway for the month of October 2023
- Bayberry
- Building Envelope
- Building Interior
- Electrical & Plumbing
- Site Improvements
- Valley View
DRG Architects shared an update and presentation at the August 29 board meeting.
- Bayberry
- Building Envelope
- Building Interior
- Electrical & Plumbing
- HVAC Systems
- Site Improvements
- Valley View
- Bayberry
- Building Envelope
- Building Interior
- Electrical & Plumbing
- Valley View