Skip To Main Content

HVAC Systems

Project Status Estimated Start Estimated Completion
Heating Systems - Unit Ventilators In Progress August 2024 December 2024
Cooling Systems - Rooftop Units In Progress August 2024 December 2024
Air Handler Unit In Progress August 2024 December 2024
Other Units (fan-coil unit. horizontal uv, cabinet htr) In Progress August 2024 December 2024
Cooling Systems - Split System Units In Progress August 2024 December 2024
Cooling Systems - Chillers, Cooling Towers, Pumps In Progress August 2024 December 2024
Exhaust Systems - Classroom Motor Replacements In Progress August 2024 December 2024
BB Exhaust Systems - Bathrooms In Progress August 2024 December 2024
ATC Systems / DDC -Expansion In Progress August 2024 December 2024
Air Filtration / Purification Systems In Progress August 2024 December 2024
HVAC for network closets In Progress August 2024 December 2024
Add A/C to gym RTU Completed August 2024 September 2024
There are no resources or collections to display