Project Status Estimated Start Estimated Completion
Concrete Sidewalks and Stairs Completed July 2023 August 2023
BB Exterior Site Lighting Completed July 2023 July 2023
Replace sidewalk under the solar canopy Completed July 2023 August 2023
ADA Compliance - addition of tactile surfaces Completed August 2023 September 2023

Updates

A list of projects which have been completed and that are underway for the month of February 2024.

  • Bayberry
  • Building Envelope
  • Building Interior
  • Electrical & Plumbing
  • Security Systems
  • Site Improvements
  • Valley View

Old Valley View sidewalk section demolition

Newly paved sidewalk section at Valley View BOE entrance

Newly paved sidewalk section at Valley View

Newly paved sidewalk section at Valley View

Newly paved sidewalk section at Valley View

Newly paved sidewalk section at Valley View

Newly paved sidewalk section at Valley View

Addition of tactile surfaces completed at Valley View

Sidewalk construction in progress at Bayberry under solar canopy

Sidewalk replacement completedĀ at Bayberry under solar canopy

BB solar canopy lighting installation

BB solar canopy lighting installation completed