Project | Status | Estimated Start | Estimated Completion |
---|---|---|---|
Concrete Sidewalks and Stairs | Completed | July 2023 | August 2023 |
BB Exterior Site Lighting | Completed | July 2023 | July 2023 |
Replace sidewalk under the solar canopy | Completed | July 2023 | August 2023 |
ADA Compliance - addition of tactile surfaces | Completed | August 2023 | September 2023 |
Updates
A list of projects which have been completed and that are underway for the month of February 2024.
- Bayberry
- Building Envelope
- Building Interior
- Electrical & Plumbing
- Security Systems
- Site Improvements
- Valley View
A list of projects that have been completed and which are underway for the month of October 2023
- Bayberry
- Building Envelope
- Building Interior
- Electrical & Plumbing
- Site Improvements
- Valley View
DRG Architects shared an update and presentation at the August 29 board meeting.
- Bayberry
- Building Envelope
- Building Interior
- Electrical & Plumbing
- HVAC Systems
- Site Improvements
- Valley View